May 2003
The engine contract was signed by Airbus Military and EPI
July 2003
Ratier was selected to supply the propeller of the A400M
March 2004
End of ‘Joint Definition Phase’, beginning of design phase and the selection of worldwide suppliers
July 2004
Preliminary design review of the TP400-D6 engine concluded
November 2004
First testing of the TP400-D6 Intermediate Pressure Compressor (IPC)
May 2005
First test of the TP400-D6 Control Monitoring System
June 2005
Assembly of the first engine for ground test
October 2005
First complete engine test
November 2005
Assembly of the first propeller
Beginning of December 2005
Delivery of the first propeller to Istres
End of December 2005
Delivery of a complete propeller to Hamilton Sundstrand, Connecticut for start of functional tests
2006
- Full engine with propeller run (February)
- A year of tests on the propeller as well as development tests on composite blades
2007
- Certification tests for blades and other components (spinner, etc.)
- First flight of the Flying Test Bed (early 2007)
- Certification of the engine, with the A400M first flight taking place shortly thereafter
End 2008
Certification of the propeller
2009
A400M entry into service